Summary
This article describes the workflow to manually specify the Date field value when creating new features in ArcMap.
Procedure
Although it is not possible to dynamically auto-populate a Date field with the current date for each newly created feature, it is possible to specify the date a feature was created manually by changing the Date field's default value inside of a feature's Template Properties dialog box.
- Right-click the desired layer in the Table of Contents and click Open Attribute Table.
- Select the Table Options drop-down and click Add Field.
- Name the field 'DATE_MOD', select the field type Date, and click OK.
- Right-click the layer in the Table of Contents once more and click Edit Features > Start Editing.
- Once the Create Features window appears, right-click the feature template for the desired layer and click Properties.
- Click the <Null> value next to the Date field and select the date from the calendar drop-down. Click Apply and OK.