When adding a TIN where the projection differs from that of the ArcScene document, it takes a much longer time to display than if the ArcScene projection and TIN projection match.
Last Published: August 25, 2014ArcGIS for Desktop
Bug ID Number
NIM058154
Submitted
June 9, 2010
Last Modified
June 5, 2024
Applies to
ArcGIS for Desktop
Version found
9.3.1
Status
Known Limit
After review by the development team, it has been determined that this issue is related to a known limitation with the software that lies outside of Esri's control. The issue's Additional Information section may contain further explanation.
Additional Information
No Public Explanation
Workaround
Keep the ArcScene projection the same projection as the TIN.